Counterweight (balance weight) installation and construction technology

Abstract: in order to strengthen the quality management of construction engineering, unify the construction technology of enterprise elevator installation engineering, and ensure the engineering quality, this process standard is formulated. This process standard is applicable to the installation and construction works of electric driven traction or forced elevator, hydraulic elevator guide rail support and guide rail. This process standard is not applicable to the installation project of sundry elevator

key words: construction process of elevator installation engineering Untitled Document 1 General 1.1 in order to strengthen the quality management of construction engineering, unify the construction process of enterprise elevator installation engineering, and ensure the project quality, this process standard is formulated. 1.2 this process standard is applicable to the installation of counterweights (counterweights) of electric driven traction or forced elevators and hydraulic elevators. 1.3 this process standard should be used in conjunction with the national standard unified standard for construction quality acceptance of building engineering gb5, which is affected by factors such as production technology and market capacity. It should be pointed out that the code for acceptance of construction quality of elevator engineering GB is used in conjunction. 1.4 this process standard is the minimum requirement for the quality of elevator installation engineering, and the specified items must be qualified. 1.5 the quality acceptance of elevator installation engineering shall not only implement this process standard, but also comply with the provisions of current relevant national standards. 2 terminology 2.54 ordinary concrete small hollow block 1 elevator installation project the process from the product of the elevator manufacturer after leaving the factory, assembled into a complete machine on the construction site to delivery. Note: the "elevator" in this process standard refers to the traction or forced elevator and hydraulic elevator driven by electricity. 2.0.2 quality acceptance of elevator installation works on the basis of performing quality inspection, the supervision unit (or construction unit), civil construction unit, installation unit and other parties jointly review the quality control data, concealed works, construction inspection records and other archival materials of the installation works, conduct general survey and machine operation assessment of the installation works, and conduct full inspection of the main control items and sampling inspection of general items, Confirm the inspection results of elevator installation engineering quality in writing according to this process standard. 2.0.3 civil handover inspection before elevator installation, the supervision unit (or construction unit), civil construction unit and installation unit shall jointly inspect the elevator shaft and machine room (if any) according to the requirements of this process standard, and check the chain reaction caused by overload, so as to confirm the installation conditions of the elevator. 3 basic requirements 3.1 the quality management of the construction site of the installation unit shall comply with the following provisions: 3.1.1 it has perfect acceptance standards, installation process and construction operation procedures. 3.1.2 have a sound installation process control system. 3.2 the construction quality control of elevator installation engineering shall comply with the following provisions: 3.2.1 before elevator installation, civil handover inspection shall be carried out according to this process standard, and the "elevator installation Civil handover quality acceptance record form" shall be filled out. 3.2.2 before elevator installation, elevator equipment mobilization acceptance shall be carried out according to this process standard, and the "elevator installation engineering equipment mobilization quality acceptance record form" shall be filled out. 3.2.3 each sub project of elevator installation shall be subject to quality control according to this process standard, and each sub project shall have self inspection records. 3.3 the quality acceptance of elevator installation works shall comply with the following provisions: 3.3.1 personnel participating in the construction and quality acceptance of installation works shall have corresponding qualifications. 3.3.2 the unit undertaking relevant safety performance testing must have corresponding qualifications. The instruments and equipment shall meet the accuracy requirements and be within the validity period of verification. 3.3.3 the quality acceptance of subdivisional works shall be carried out on the basis that the elevator installation unit has passed the self inspection. 3.3.4 the quality of subdivisional works shall be inspected and accepted according to the main control items and general items respectively. 3.3.5 after the elevator installation unit passes the inspection, the concealed works shall be notified to the relevant units for inspection and acceptance before concealment, and the acceptance documents shall be formed. 4 general provisions 4.1 when the counterweight (balance weight) frame has a reverse rope sheave, the reverse rope sheave should be equipped with protective devices and rope retaining devices. 4.2 counterweight (counterweight) block shall be fixed reliably. 5 construction preparation 5.1 requirements for mobilization acceptance and retest of materials, finished products, semi-finished products, components and fittings 5.1.1 the specification of counterweight (counterweight) frame shall meet the design requirements, be complete, firm, and free of distortion and damage. 5.1.2 the specification, quality and quantity of counterweight (counterweight) guide shoes and screws for fixing guide shoes shall meet the requirements. 5.1.3 the adjusting gasket shall meet the requirements. 5.2 construction machines and tools, equipment, construction site requirements 5.2.1 main machines and tools: chain fall, steel wire rope buckle, timber. 5.2.2 operation conditions: 1. After the installation, adjustment and acceptance of counterweight (counterweight) guide rail, remove local scaffold gears on the bottom floor, subject to the counterweight (counterweight) entering the shaft and in place. 2. The electric welding handle wire and lighting wire in the shaft are well arranged, and there is a convenient operation site. 6 construction process 6.1 process flow: preparation before hoisting → hoisting of counterweight (counterweight) frame in place → installation and adjustment of counterweight (counterweight) guide shoe → installation and fixation of counterweight (counterweight) block. 6.2 preparations before hoisting: 6.2.1 set up an operation platform at the corresponding position on the scaffold (subject to the convenience of hoisting the counterweight (counterweight) frame and loading the lump) (Fig. 6.2.1). Figure 6.2.16.2.2 fasten the steel wire rope buckle on the two opposite counterweight (counterweight) guide rail brackets at an appropriate height (subject to the convenient lifting of counterweight (counterweight)), and hang a chain fall in the center of the steel wire rope buckle. The steel wire rope buckle shall be tied to the guide rail support, and cannot be directly tied to the guide rail, so as to avoid displacement or deformation of the guide rail after being stressed. 6.2.3 support one 100mm on both sides of counterweight (balance weight) buffer × 100mm batten. Timber height c=a+b+ over distance (Figure 6.2.3). See table 6.2.3 for the over distance. Figure 6.2.3 overtravel distance table 6.2.3 elevator rated speed (m/s) buffer type overtravel distance (mm)

Copyright © 2011 JIN SHI